Critical Path (CPM) for a classroom timetable

Built for students learning it for a class or exam. See the concept move instead of memorizing formulas — and check your homework intuition. Simulate a classroom timetable live below — adjust the inputs and watch it respond, right in your browser.

Critical Path MethodLive

Controls

Presets

The Critical Path Method finds the longest chain of dependent tasks through a project — the sequence that sets the minimum completion time. Tasks on it have zero slack: delay any one and the whole project slips. Tasks off it can float. Stretch task B or D and watch the critical path re-route. The backbone of project management.

▶ Run in Python

Data Inspector

Project duration15 days
Critical tasksA, B, D, F
Tasks6
Reading this result: The critical path is A → B → D → F at 15 days. Tasks C, E carry slack — delaying them will not move the finish date, but any slip on a critical task pushes the whole project.

Governing equation

Runs locally in your browser — free forever. Scale to the cloud when reality gets heavy.

or unlock everything with Pro →

More with Critical Path (CPM)

Frequently asked questions

Is this good for students?
Yes — this version of "Critical Path (CPM) for a classroom timetable" is framed for students learning it for a class or exam. See the concept move instead of memorizing formulas — and check your homework intuition.
Do I need to install anything?
No. It runs in any modern browser, free, with no account required.