For Hobbyists & Makers · Critical Path (CPM)
Critical Path (CPM) for a supply chain
Built for hobbyists & makers exploring it for fun. Play with real physics and math, no license and no setup — just open and tinker. Simulate a supply chain live below — adjust the inputs and watch it respond, right in your browser.
Critical Path MethodLive
project scheduling
Controls
Presets
The Critical Path Method finds the longest chain of dependent tasks through a project — the sequence that sets the minimum completion time. Tasks on it have zero slack: delay any one and the whole project slips. Tasks off it can float. Stretch task B or D and watch the critical path re-route. The backbone of project management.
Data Inspector
Project duration15 days
Critical tasksA, B, D, F
Tasks6
Reading this result: The critical path is A → B → D → F at 15 days. Tasks C, E carry slack — delaying them will not move the finish date, but any slip on a critical task pushes the whole project.
Governing equation
Runs locally in your browser — free forever. Scale to the cloud when reality gets heavy.
More with Critical Path (CPM)
Critical Path (CPM) for a delivery routeCritical Path (CPM) for a warehouse layoutCritical Path (CPM) for a factory scheduleCritical Path (CPM) for a staff rosterCritical Path (CPM) for a portfolio mixCritical Path (CPM) for a bin-packing planCritical Path (CPM) for a knapsackCritical Path (CPM) for a network flow
Frequently asked questions
- Is this good for hobbyists & makers?
- Yes — this version of "Critical Path (CPM) for a supply chain" is framed for hobbyists & makers exploring it for fun. Play with real physics and math, no license and no setup — just open and tinker.
- Do I need to install anything?
- No. It runs in any modern browser, free, with no account required.